Short answer
Commercial painting price per square foot = (hours on site × painters × loaded wage + paint and sundries + overhead) ÷ (1 − margin) ÷ area. Example: 6,800 sq ft of office walls, four painters at 45 sq ft an hour each, prices at $11,844.62, or $1.742 per sq ft.
- Each surface needs its own rate: on the assumed inputs, office walls price at $1.742 and CMU block at $4.015 per sq ft.
- The example floor bids at $48,799.43: $4.067 per floor sq ft, $2.176 per painted sq ft.
- Small areas cost more per sq ft: $2.565 at 500 sq ft, $1.777 at 10,000, same crew and rates.
- More painters shorten the schedule, not the price: 9.45 days with two, 3.15 with six.
- A 10% retainage holds back $4,879.94, about 33% of the job's profit, until completion.
On this page
- How much can I charge for a commercial paint job per square foot?
- Commercial painting price per square foot calculator
- Commercial painting production rates: price per square foot by surface
- Wall area vs floor area: measuring a commercial take-off
- Mobilisation, lifts and protecting an occupied building
- Night, weekend and after-hours work: what it does to the rate
- Crew size vs schedule: 2, 4 or 6 painters
- How much should I charge to paint 500 or 1,000 square feet?
- Retainage, prevailing wages and rules that change the hours
- What a commercial painting bid sheet holds, and which tool to use
- Step-by-step
- FAQ
How much can I charge for a commercial paint job per square foot?
Charge each surface's break-even divided by one minus your margin, then divide by its area. Price per square foot is an output of the bid, not a number you copy from a cost page.
- Hours on site = area ÷ (your production rate per painter × painters).
- Crew hours = hours on site × painters.
- Materials = gallons (area × coats ÷ coverage, rounded up) × price a gallon + sundries.
- Break-even = crew hours × (loaded wage + overhead per crew hour) + materials.
- Price = break-even ÷ (1 − margin); price per sq ft = price ÷ area.
I build pricing maths; I do not run a painting crew. Every rate, wage and gallon below is an assumption for a four-painter crew. Replace each one with your own timed jobs and invoices.
Labour and overhead (assumed): a $27 wage plus 32% burden is $35.64 an hour. If you are self-employed, the IRS puts the self-employment tax rate at 15.3%, one part of that burden; the labor burden calculator guide builds the rest. Overhead of $52,000 a year over 4 people × 230 billable days × 8 hours (7,360 hours) is $7.07 per crew hour. Break-even is $42.71 a crew hour; divided by 0.70 it sells at $61.01.
Commercial painting price per square foot calculator
Enter the area, your crew's production rate, painters, wage, materials, overhead and margin. It opens on the office walls of the example floor and shows $11,844.62, or $1.742 per sq ft.
The production rate field is the crew's rate: 45 sq ft an hour per painter × 4 painters = 180. Hours on site are 6,800 ÷ 180 = 37.78; the crew works 151.11 crew hours. Paint is 6,800 × 2 coats ÷ an assumed 320 sq ft a gallon = 43 gallons, rounded up.
Worked example: Office walls on the example floor: 6,800 sq ft of drywall, 2 coats, four painters at an assumed 45 sq ft an hour each (crew rate 180); materials = 43 gallons at an assumed $38 + $0.03 a sq ft of sundries (all inputs are assumptions)
| Item | Value |
|---|---|
| Workers (input) | 4 |
| Hourly wage paid (input) | $27.00 |
| Labour burden % (input) | 32% |
| Materials (input) | $1,838.00 |
| Overhead for the year (input) | $52,000.00 |
| People in the field (input) | 4 |
| Billable days a year (input) | 230 |
| Target margin % (input) | 30% |
| Jobs a week (input) | 1 |
| Area (sq ft) (input) | 6,800 |
| Production rate (sq ft per hour) (input) | 180 |
| Loaded labour rate (per hour) | $35.64 |
| Crew-hours | 151.11 |
| Labour cost | $5,385.60 |
| Overhead per sellable hour | $7.07 |
| Overhead share | $1,067.63 |
| Break-even cost | $8,291.23 |
| Price to quote | $11,844.62 |
| Profit on the job | $3,553.39 |
| Price if you MARK UP instead | $10,778.60 |
| Margin you actually keep with markup | 23.08% |
| Lost per job by marking up | $1,066.02 |
| Lost per year by marking up | $55,432.81 |
| Hours on the job | 37.78 |
| Price per sq ft | $1.742 |
| Break-even per sq ft | $1.219 |
Computed with the same formulas as the free calculators on this site. Change any input in the calculator above to see your own numbers.
Check it: 151.11 crew hours × $35.64 = $5,385.60, plus $1,067.63 of overhead and $1,838.00 of materials, is $8,291.23. Divided by 0.70 that is $11,844.62. The free painting estimate calculator runs the same maths from painting hours in place of area.
Commercial painting production rates: price per square foot by surface
A commercial floor is several jobs in one. Each surface below has its own assumed rate per painter, coats and coverage, so its own price per square foot. Every row is one pricing_math run with the same crew and overhead.
| Surface | Area (sq ft) | Rate per painter (sq ft/hr) | Hours on site | Materials | Price | Price per sq ft |
|---|---|---|---|---|---|---|
| Office walls, drywall, 2 coats | 6,800 | 45 | 37.78 | $1,838 | $11,844.62 | $1.742 |
| Corridor walls, many doors to cut around, 2 coats | 2,822 | 30 | 23.52 | $796.88 | $6,877.17 | $2.437 |
| Drywall ceilings, 2 coats | 4,000 | 35 | 28.57 | $1,038 | $8,455.14 | $2.114 |
| CMU block walls: block filler + 2 finish coats | 1,600 | 20 | 20 | $1,080 | $6,423.45 | $4.015 |
| Exposed deck and joists, spray, 1 coat (plan area) | 7,200 | 110 | 16.36 | $1,224 | $5,741.79 | $0.797 |
| Doors and frames, per each (36 at 0.8 painter hours + $9 each) | 7.2 | $324 | $2,219.87 | $61.66 a door |
The CMU row carries an extra pass: block filler at an assumed 90 sq ft a gallon before the two finish coats, so it costs $4.015 a sq ft against $1.742 for drywall. The sprayed deck is fast per square foot but needs a lift, which is priced once, in mobilisation below. Doors are counted, not measured: $61.66 each here.
Why one blended rate misprices. This floor averages $2.176 per painted sq ft. Bid a 10,000 sq ft all-CMU job at that rate and you quote $21,760; its own build-up breaks even at $27,972.61, so the blended price is $6,212.61 below cost before any profit.
Wall area vs floor area: measuring a commercial take-off
Measure surfaces, then report the bid per floor square foot as well, because the owner or general contractor will compare on floor area. The residential version of this trap is in the painting price per square foot guide.
| Surface | Working | Sq ft |
|---|---|---|
| Perimeter walls | 2 × (120 + 100) × 10 ft = 4,400, less 1,200 of glass | 3,200 |
| Office partitions | 180 linear ft × 10 ft × 2 faces | 3,600 |
| Corridor walls | 160 linear ft × 10 ft × 2 faces = 3,200, less 18 doors × 21 | 2,822 |
| CMU cores | 160 linear ft × 10 ft | 1,600 |
| Drywall ceilings | ceiling area = the floor area under it | 4,000 |
| Exposed deck | 12,000 floor − 4,000 drywall ceiling − 800 of cores | 7,200 |
The floor is 120 × 100 = 12,000 sq ft, but the take-off paints 22,422 sq ft of surface plus 36 doors. With mobilisation the bid is $48,799.43: $4.067 per floor sq ft and $2.176 per painted sq ft. Say which one a number means every time you write it down.
Mobilisation, lifts and protecting an occupied building
Set-up, daily clean-up, protection and lift time belong on their own line, priced once for the whole floor. Buried inside each surface rate, they scale with area when they do not, and a reviewer cannot see them.
Assumed here: 6 hours per painter to set up and protect desks, floors and signage on day one, 0.75 hours a day for set-up and clean-up over 17 working days (production hours ÷ 8, rounded up), and 4 hours to close out. The deck needs 1 week of lift at an assumed $700 a week; get a real quote from your own rental yard and put it here.
Worked example: Mobilisation and access for the whole floor: 22.75 hours per painter (set-up and protection 6, 0.75 a day for 17 days, close-out 4); materials = 1 week of lift at an assumed $700 + $480 of protection (assumed)
| Item | Value |
|---|---|
| Workers (input) | 4 |
| Hourly wage paid (input) | $27.00 |
| Labour burden % (input) | 32% |
| Materials (input) | $1,180.00 |
| Overhead for the year (input) | $52,000.00 |
| People in the field (input) | 4 |
| Billable days a year (input) | 230 |
| Target margin % (input) | 30% |
| Jobs a week (input) | 1 |
| Hours on the job (input) | 22.75 |
| Loaded labour rate (per hour) | $35.64 |
| Crew-hours | 91 |
| Labour cost | $3,243.24 |
| Overhead per sellable hour | $7.07 |
| Overhead share | $642.93 |
| Break-even cost | $5,066.17 |
| Price to quote | $7,237.39 |
| Profit on the job | $2,171.22 |
| Price if you MARK UP instead | $6,586.03 |
| Margin you actually keep with markup | 23.08% |
| Lost per job by marking up | $651.37 |
| Lost per year by marking up | $33,871.00 |
Computed with the same formulas as the free calculators on this site. Change any input in the calculator above to see your own numbers.
Mobilisation adds $7,237.39 to the bid. Lifts also add daily minutes: OSHA's aerial lift rule (29 CFR 1926.453) says lift controls shall be tested each day prior to use and that only authorized persons shall operate an aerial lift. Its scaffold training rule (29 CFR 1926.454) requires each employee who works on a scaffold to be trained by a qualified person. Price that time and training as hours.
Painting Estimate & Profit Calculator
A painting estimate sheet for Excel & Google Sheets. Enter each surface as square feet and the labour hours from your production rate; it adds paint from your coverage rate, drive time, extra materials such as lift rental, overhead and your margin, and shows break-even and the price to quote. It is built around rooms: it has no production-rate table, retainage or prevailing-wage cells. One-time $14.99, no subscription, instant download.
See the painting estimate spreadsheet →Buy now — $14.99All 7 templates — $49Instant access by email after checkout via Payhip. Want to try the maths first? Use the free painting estimate calculator — no signup.
Night, weekend and after-hours work: what it does to the rate
Occupied offices often want painting after hours. Model it as two input changes: a higher wage (your own premium policy) and a slower rate (furniture moved and put back, shorter shifts). Both are assumptions here: a 20% premium and 38 sq ft an hour per painter in place of 45.
Worked example: The same office walls at night in an occupied building: a 20% wage premium ($32.40) and an assumed 38 sq ft an hour per painter (all assumed)
| Item | Value |
|---|---|
| Workers (input) | 4 |
| Hourly wage paid (input) | $32.40 |
| Labour burden % (input) | 32% |
| Materials (input) | $1,838.00 |
| Overhead for the year (input) | $52,000.00 |
| People in the field (input) | 4 |
| Billable days a year (input) | 230 |
| Target margin % (input) | 30% |
| Jobs a week (input) | 1 |
| Area (sq ft) (input) | 6,800 |
| Production rate (sq ft per hour) (input) | 152 |
| Loaded labour rate (per hour) | $42.77 |
| Crew-hours | 178.95 |
| Labour cost | $7,653.22 |
| Overhead per sellable hour | $7.07 |
| Overhead share | $1,264.30 |
| Break-even cost | $10,755.52 |
| Price to quote | $15,365.03 |
| Profit on the job | $4,609.51 |
| Price if you MARK UP instead | $13,982.18 |
| Margin you actually keep with markup | 23.08% |
| Lost per job by marking up | $1,382.85 |
| Lost per year by marking up | $71,908.35 |
| Hours on the job | 44.74 |
| Price per sq ft | $2.260 |
| Break-even per sq ft | $1.582 |
Computed with the same formulas as the free calculators on this site. Change any input in the calculator above to see your own numbers.
The same 6,800 sq ft moves from $1.742 to $2.260 per sq ft, $3,520.41 more for the wall line. Quote night work as its own line so the owner can see the trade-off.
Crew size vs schedule: 2, 4 or 6 painters
Adding painters shortens the calendar, not the crew hours, so the price stays the same while the per-painter rate holds. What changes is how many days the site is disrupted.
| Painters | Crew rate (sq ft/hr) | Hours on site | Working days (8 h) | Crew hours | Price |
|---|---|---|---|---|---|
| 2 | 90 | 75.56 | 9.45 | 151.11 | $11,844.62 |
| 4 | 180 | 37.78 | 4.72 | 151.11 | $11,844.62 |
| 6 | 270 | 25.19 | 3.15 | 151.11 | $11,844.62 |
Overhead per crew hour uses the 4 people you have in the field across the year, not the size of this one crew. If six painters get in each other's way and the rate per painter drops, the price rises: rerun the row with the slower rate.
How much should I charge to paint 500 or 1,000 square feet?
Small areas cost more per square foot because set-up and clean-up do not shrink. Each row is one job() run: two painters, 45 sq ft an hour each, 3 hours on site of set-up and clean-up, paint rounded up to whole gallons.
| Area (sq ft) | Hours on site | Gallons | Materials | Price | Price per sq ft |
|---|---|---|---|---|---|
| 500 | 8.56 | 4 | $167 | $1,282.48 | $2.565 |
| 1,000 | 14.11 | 7 | $296 | $2,144.62 | $2.145 |
| 2,500 | 30.78 | 16 | $683 | $4,731.06 | $1.892 |
| 5,000 | 58.56 | 32 | $1,366 | $9,096.08 | $1.819 |
| 10,000 | 114.11 | 63 | $2,694 | $17,771.83 | $1.777 |
On these inputs 500 sq ft prices at $1,282.48 and 1,000 sq ft at $2,144.62. Use the smallest row as your minimum charge for a service call. A per-square-foot number from a big job, applied to a small one, loses money.
Retainage, prevailing wages and rules that change the hours
Retainage. Many contracts hold back part of each payment until completion. On federal construction contracts, FAR 32.103 says retainage shall not exceed 10 percent of the approved estimated amount. Private contracts set their own terms; read yours. At 10% the example bid of $48,799.43 has $4,879.94 held, about 33% of its $14,639.83 profit, so you carry the labour and paint costs until the final payment.
Public jobs. FAR 22.403-1 says federal contracts in excess of $2,000 for construction, alteration or repair (including painting and decorating) of public buildings shall contain a clause that no laborer or mechanic employed on the site receives less than the prevailing wage rates as determined by the Secretary of Labor. Put the wage from the contract's wage determination in the wage field; this page quotes no rates.
Lead. OSHA's lead standard for construction (29 CFR 1926.62) applies where an employee may be occupationally exposed to lead and defines construction work to include painting and decorating. The EPA RRP rule covers firms whose work disturbs lead-based paint in homes, child care facilities and kindergartens built before 1978. Testing, containment and training are hours and materials you add to the line.
VOC limits. The EPA's national VOC standard for architectural coatings (40 CFR part 59, subpart D) works by requiring manufacturers and importers to limit the VOC content of architectural coatings, so the product label is where the limit shows up. States and air districts may set their own limits; ask the local air agency before you specify products. None of this is legal advice: check with the contracting officer or a licensed professional.
What a commercial painting bid sheet holds, and which tool to use
One line per surface, with the inputs visible, so a reviewer can check every number. Here is the office-wall line from the example:
| Column | Example |
|---|---|
| Surface and coats | Drywall walls, 2 coats |
| Area | 6,800 sq ft |
| Rate per painter × painters | 45 × 4 = 180 sq ft/hr |
| Hours on site / crew hours | 37.78 / 151.11 |
| Gallons | 43 |
| Labour / materials / overhead | $5,385.60 / $1,838 / $1,067.63 |
| Equipment | none on this line; the lift sits in mobilisation |
| Price / per sq ft | $11,844.62 / $1.742 |
Hours on site
=B2/(B3*B4)B2 = area, B3 = your rate per painter (sq ft/hr), B4 = painters. Put in B12.
Gallons
=ROUNDUP(B2*B5/B6,0)B5 = coats, B6 = coverage in sq ft per gallon. Put in B13.
Line price
=ROUND((B12*B4*(B7*(1+B8)+B9/B10)+B13*B11+B2*B14)/(1-B15),2)B7 = wage, B8 = burden %, B9 = yearly overhead, B10 = sellable crew hours a year, B11 = price a gallon, B14 = sundries per sq ft, B15 = margin %. Put in B16.
Price per sq ft
=ROUND(B16/B2,3)Per painted sq ft for this line.
Price per floor sq ft
=ROUND(SUM(B16:H16)/B20,3)Sum of every line incl. mobilisation, divided by the floor area in B20.
Retainage held
=ROUND(SUM(B16:H16)*B21,2)B21 = the retainage % in your contract.
The markup mistake: adding 30% to break-even bills $10,778.60 for the wall line and keeps 23.08%, not 30%: $1,066.02 short. The markup vs margin calculator guide has the chart.
Tools. The calculator above prices one surface at a time. The painting estimate spreadsheet ($14.99) holds up to 12 rooms or surfaces: each row takes square feet and labour hours and returns gallons, paint cost, labour and a line total, then adds crew size, drive time, extra materials, overhead per crew-hour, break-even, the price at your margin and price per sq ft. It is built around rooms and has no production-rate table, retainage or prevailing-wage cells: enter each commercial surface as its area plus the hours from your rate, and put lift rental in extra materials. See what the painting estimate spreadsheet includes. For the residential room method, read how to bid a painting job; for what the customer document holds, the painting estimate template guide.
Step-by-step: Commercial Painting Price per Square Foot: Price Each Surface
- Take off each surface. Measure walls as linear feet × height less large openings, ceilings as the floor area under them, and count doors.
- Set a rate per surface. Use your own timed production per painter for each surface and coat count, then multiply by painters for the crew rate.
- Cost paint by coverage. Gallons = area × coats ÷ coverage, rounded up, times your price a gallon, plus sundries.
- Price each line. Crew hours × (loaded wage + overhead per crew hour) + materials, divided by (1 − margin).
- Add mobilisation and access. Price set-up, protection, daily clean-up and lift weeks once, as their own line.
- Check per floor sq ft and terms. Divide the total by floor area, then check retainage, wage rules and lead or VOC requirements in the contract.
Painting Estimate & Profit Calculator
A painting estimate sheet for Excel & Google Sheets. Enter each surface as square feet and the labour hours from your production rate; it adds paint from your coverage rate, drive time, extra materials such as lift rental, overhead and your margin, and shows break-even and the price to quote. It is built around rooms: it has no production-rate table, retainage or prevailing-wage cells. One-time $14.99, no subscription, instant download.
See the Painting Estimate & Profit Calculator →Buy now — $14.99All 7 templates — $49Instant access by email after checkout via Payhip. Want to try the maths first? Use the free calculator — no signup.
Frequently asked questions
How much can I charge for a commercial paint job per square foot?
Charge your break-even for that surface divided by one minus your margin, then divide by area. On this page's assumed inputs, office walls price at $1.742 per sq ft and CMU block at $4.015. Replace the rates, wage and overhead with your own.
How do you estimate a commercial painting job?
Take off every surface from the drawings, give each its own production rate and coat count, cost the paint from coverage, price each line on margin, add mobilisation and lift time once, then divide the total by the floor area to compare with other bids.
How much should I charge to paint 1,000 square feet?
On the assumed inputs, two painters repainting 1,000 sq ft of office walls with 3 hours of set-up price at $2,144.62, or $2.145 per sq ft. The same crew at 10,000 sq ft is $1.777, because set-up is spread wider.
How much to charge for painting 500 square feet?
On the same assumptions 500 sq ft prices at $1,282.48, which is $2.565 per sq ft. Small areas carry the full set-up and a whole gallon minimum, so treat that row as a minimum charge rather than a per-foot rate.
Do prevailing wages apply to commercial painting?
On federal jobs they can. FAR 22.403-1 says federal contracts over $2,000 for construction, alteration or repair, including painting and decorating, of public buildings must carry a prevailing-wage clause. Use the rate in the contract's wage determination as your wage input.
How much retainage is held on a painting contract?
Whatever your contract says. For federal construction contracts, FAR 32.103 caps retainage at 10 percent of the approved estimated amount. On the example bid, 10% is $4,879.94 held until completion, about 33% of the job's profit.
Should I price commercial painting per square foot or per hour?
Build it from hours, then show it per square foot. Hours come from area ÷ your crew's rate; the per-square-foot figure is the result. The example wall line is $11,844.62 for 151.11 crew hours, which is $1.742 per sq ft.
Sources
- IRS: Self-employment tax (Social Security and Medicare taxes) — The self-employment tax rate is 15.3%
- FAR 22.403-1: Construction Wage Rate Requirements statute — Federal contracts in excess of $2,000 for construction, alteration or repair (including painting and decorating) of public buildings carry a prevailing-wage clause; rates determined by the Secretary of Labor
- FAR 32.103: Progress payments under construction contracts — Retainage withheld shall not exceed 10 percent of the approved estimated amount
- OSHA 29 CFR 1926.453: Aerial lifts — Lift controls shall be tested each day prior to use; only authorized persons shall operate an aerial lift
- OSHA 29 CFR 1926.454: Training requirements (scaffolds) — Each employee who performs work on a scaffold is trained by a person qualified in the subject matter
- OSHA 29 CFR 1926.62: Lead (construction) — Applies to construction work where an employee may be exposed to lead; construction work includes painting and decorating
- US EPA: Lead Renovation, Repair and Painting Program Rules — Firms disturbing lead-based paint in homes, child care facilities and kindergartens built before 1978 must be certified
- US EPA: Architectural Coatings, National Volatile Organic Compounds Emission Standards (40 CFR Part 59 Subpart D) — The rule requires manufacturers and importers to limit the VOC content of architectural coatings